  • What are the preparations for switchboard surveys?

    What are the preparations for switchboard surveys?

  • #2

    Switchboard Survey:
    • Thorough cleaning internally and externally at switchboard, when all generators are stopped and their prime movers locked off.
    • Main bus bar and their connections checked for tightness.
    • Bus bar supports, checked for damage due to insulation material.
    • Overheating signs at connection junctions, due to loose joint.
    • Internal wiring securely fixed.
    • Cable entries at switchboard bottom, sealed with non-flammable material.
    • Earth bar, securely bonded to both frame and to the ship hull.
    • Hinged panel door bonded with an earth strap to main switchboard frame.
    • Insulation resistance of each terminal measured.
    • Voltmeters, Watt meters and Ammeters calibrated and tested.
    • All trips tested [Safety devices].
    • Synchronizing test [load sharing] demonstrated.
    • Earth lamps checked
    • Automatic circuit breakers (ACB) and Automatic voltage regulator (AVR) tested.

    Comment


    • #3
      thanks for this information
      Following survey items generally apply to all ships:
      1. Generators and governors.
      2. Circuit breakers
      3. Switchboard and fittings (main and emergency switchboard, distributor switchboard).
      4. Cables
      5. Insulation resistance
      6. Motors and Starters
      7. Emergency power equipment
      8. Parts of steering gear
      9. Navigation light indicator